Case study · Construction · 2026

Girdernote.

A site project tracker for a small building contractor: programme, site diary, snags on the plan and running bills.

Industry
Construction & contracting
Platform
Desktop, tablet, phone
My role
UI/UX + front-end
Year
2026
Girdernote walkthrough video, first frame
01

Overview

A phase programme, a daily site diary and snags on the floor plan for a small building contractor, in a single web app. Plus materials, labour, running bills, drawings and safety.

Who is it for?

OFFICEThe project manager plans phases, approves drawings and certifies bills.
SITEThe supervisor files the day's log and drops snag pins from a phone.
CLIENTGets a clear update, written from the site diary.
02

Problem → solution

Everyday pains on a small building job, and what the app does about each one.

  • Problem 01

    The site diary is a paper book the office never sees.

    What the app does

    The day is logged on a phone in under a minute.

  • Problem 02

    Snags get lost in chat photos and phone calls.

    What the app does

    Each snag is a pin on the floor plan, with room, trade and fix-by date.

  • Problem 03

    One late phase quietly pushes the handover date.

    What the app does

    Move a phase and every later phase follows, with the new handover.

03

Key features

SNAGS ON THE PLAN

Pin the snag. Stamp it closed.

Snags live on the drawn floor plan, not in a chat. Tap the spot and the room fills itself in.

Girdernote: Pin the snag. Stamp it closed.
Tap the planPress Drop a snag pin, then tap the spot. Esc cancels.
The room fills itself inThe form opens with the room picked up from the pin.
Closed with a stampFixed by the trade, checked by the engineer, then stamped.
PROGRAMME

Drag one phase. The rest follow.

Move a bar or stretch its end. Linked phases after it move too, and Undo puts every one back.

Girdernote: Drag one phase. The rest follow.
New dates as you dragA tooltip shows the new start, end and length.
Later phases followLinked phases get a yellow ring and move by the same days.
Every delay, explainedAdd one after the drop. It goes in the delay register.
DAILY SITE LOG

The day's log in under a minute.

Made for a supervisor on a slab with one free hand. A draft is kept on the phone.

Girdernote: The day's log in under a minute.
Weather, labourTap the weather. Headcounts come in from the last log.
Work doneTap the phases that moved and set their progress.
Photo, then FileDiary, labour sheet and programme update together.
04

On a phone

Made for the site, too. A bottom bar with Log today in the middle, and windows that turn into sheets.

Girdernote on a phone
05

Design system

Drawn like a blueprint. Blueprint blue for action, chalk for highlights, safety yellow only for warnings.

Blueprint blue#1D4E89
Chalk#DDF1FF
Blueprint paper#EEF3F8
Ink#12243A
Safety yellow#FFD400
Done#2B7A50
Open snag#B5372A
Night blueprint#0B1A2E

Type: Rubik

Girdernote design system
06

How it was built

  • Plain HTML, CSS and JavaScript: no framework, fast on a phone.
  • Built with AI-assisted development: I set the brief, flows and design rules, then directed and reviewed the code.
  • Light and dark mode, and layouts for desktop, tablet and phone.
  • Sample data that moves with today's date and is saved in the visitor's browser.
  • An automated end-to-end test (Playwright) clicks every button, and runs again on fixed dates such as 31 December and 1 April.
  • Concept project: the brand, people and data are fictional.